Scope of Work

➢ Scope shall cover the complete scope, concerning the review of the sea wall and associated works. 
➢ Review of the Design of Temporary works necessary concerning the sea wall and associated work and equipment. 
➢ Detailed design and deliverables for the sea wall and associated works. Bund and ground treatment and Seawall designs review for the entire Package.

Project Description

Package IV, Princes Street Flyover to Priyadarshini Park consists of a grade road, transition ramp, cut & cover tunnel, TBM tunnel, reclamation, and seawall. This package extends from CH 1+975 to CH 5+900 and is mostly an underground road, except for the entry and exit of the tunnel.

➢ Construction Reference Drawings This means those drawings referred to in Clause C2 (8) of the Employer's Requirements Section C - Design in respect of which a Notice to Proceed has been issued.
➢ Definitive Design This means the detailed design is fully coordinated and interfaced, complete in all respects based on the Noticed Preliminary Design.
➢ Review of specification The specification proposed by the Contractor both for reclamation and sea wall construction shall be reviewed. The review shall be based on the Indian and International codes as defined in the Design Basis Report. 
➢ Final Design This shall be the design calculations corresponding to the as-built drawings and to be submitted together with the as-built drawings.
 

 

  • Client:MMRDA / M/s SMEC India Pvt. Ltd.
  • Location:Princes Street Flyover to Priyadarshini Park
  • tenure:2019 - 2021